preparing for concrete slab
Photographic Journal of our Building Progress
on the House to Lockup
2 May'03 Digging the Hole 2 March'04
22 March'03 Pouring the Slab(s) 16 March'04 Preparing to Enclose Upstairs
12 June'03 A Lump of Wood or Two 28 March'04 The Boards
18 April'03 Putting on the Lid 11 May'04 Bricks, bricks and more bricks
17 June'03 Upright Already 4 June'04 Help from Adam & Justine
27 June'03 Beams and Windows 10 July'04 Our Snazzy Window
17 July'03 The Top Storey 31 July'04 Bits & Pieces
30 July '03 A Different Perspective 31 Aug'04 Lining Walls & the First Door
6 Aug '03 Now it's all up to Us! 21 Sept'04 Even the Kitchen Sink
1 Oct'03 Great Sadness 24 Sept'04 Windows at Last
15 Oct'03 The First Roof 29 Sept'04 Rendering the Walls
25 Oct'03 Our Mudbricks Arrive 24 Nov'04 The Bathroom
7 Nov'03 An Initiation into Scaffolding 10 Dec'04 Moving In!
9 Nov'03 Another Crack at the Roof 16 Dec'04 The Day of the Duck
25 Nov'03 The High Roof 25 Jan'05 Back to Work
27 Nov'03 Bricklaying at Last! 9/17 Feb'05 Scaling the Heights
3 Jan'04 Family Joins in Again 18 March'05 Last Brick in the Last Wall
20 Jan'04 Bringing in the Bricks 26 March'05 And a Front Door Too
30/31 Jan& 2 Feb Ollie's New Toy on theJob 8 April'05 Lock Up!!!
24 Feb'04 Nick Puts it Straight